A waste treatment facility that included a 1800m2 hall, a 170m2 office and a civilian shelter.
Date: 08/2020-03/2021
Weight of the steels approx.: 85,000 kg
Project size: ~0.9 m€
Form of contract: Total price contract
The Hall, Office and Population Shelter were built on top of piles. The frame of the hall is steel and the surface cladding is sheet metal.
The frame of the two-story office is made of steel and the cladding is metal-wool-metal elements. Civil protection is reinforced concrete
structured.
The waste treatment plant processes construction and demolition waste, sorting the waste for recycling